2012-01-04 13.24.45

This project was a real challenge being over 3 floors at split level meaning that the basement had to be ‘tanked’ to prevent water ingress. The rear of the house was in fact 8feet below the level at the front door. 1st photo – “Before” – with conservatory on rear.

 

2012-01-04 13.26.34

View from old conservatory

2012-01-12 12.47.28

Site cleared

2012-01-12 12.48.46

Excavation of footings

2012-01-19 15.13.27

Basement blockwork taking shape

2012-01-19 15.15.47

Retaining wall to create level site

2012-02-16 09.18.06

Crane arrives to lift steels

2012-02-16 09.25.15

Steels lifted over house

2012-02-16 09.31.21

One steel in position on padstones

2012-02-16 09.33.09

2nd lift scaffold for 1st floor construction

2012-04-11 11.37.53

Roof and fascia complete and scaffold down

2012-04-11 12.40.11

Roof insulation

2012-04-14 14.48.49

Windows in

2012-04-14 14.49.27

Basement floor insulation arrives

2012-04-14 15.26.16

Plasterboarding main lounge

2012-04-21 08.03.03

Water-proof tanking for basement floor and walls

2012-04-21 09.32.49

Basement floor insulated and floorbords being fitted

2012-05-05 15.06.03

Basement plastered, radiator in place and electrics 2nd fixed

2012-05-05 15.04.03

Top floor bedroom complete with skirting boards

2012-05-05 15.04.24

En-suite plastered ready for shower suite fitting and tiling

2012-05-05 15.04.43

Bedroom complete with corner en-suite

2012-05-05 15.05.03

View from bedroom across flat lead roof

2012-05-05 15.06.57

Bifold doors in – water-tight lounge/diner

2012-05-05 15.10.27

Rainwater goods complete outside – awaiting balcony deck and balustrade

2012-05-30 13.19.12

Time for the side utility extension

2012-05-30 13.20.07

Side utility with store under

DSCF3419

Fabulous lounge view – better than before!

DSCF3420

Completed balcony with steps to the garden

DSCF3418

The finished job!

DSCF3421

Finally “After” with steps and patio complete